January 12, 2015 The PennDOT wall is complete! The PennDOT Wall is complete
December 31, 2014 The PennDOT wall installation project in Raubsville is coming to a close!
December 19, 2014 The PennDOT wall installation project in Raubsville and the Lock 20 bypass project in Kintnersville are on schedule to be completed early in January. When finished, the Park staff plans to allow the Lehigh River water to freely flow s …
December 8, 2014 This weekend’s rain helped to fill the Canal with runoff, especially in the Point Pleasant area. The Park’s work on decreasing the leakage at waste gates is working. Here’s a photo taken yesterday at the Lock 14 bypass in Point Pleasan …
November 20, 2014 The water level has risen quickly in New Hope. In fact, it’s at its highest level in recent memory.
November 17, 2014 A second inspection revealed that the Lock 20 bypass pipe needs to be replaced entirely or slip-lined. Stay tuned.
November 15, 2014 The Centre Bridge pump stopped operating reliably late in the week, mostly being in the off mode. The water level dropped dramatically from Centre Bridge to New Hope.
November 10, 2014 The Lock 20 bypass pipe is in better shape than anticipated. Only the end is affected, so the project will take less time and be less expensive.