Progress Report
Now that twelve different flood repair and capital project contracts are in various stages of completion, keeping track of progress is quite a task. In an effort to make the information about each contract and the project as a whole more understandable, the chart below was developed.
The data shown is as of 6/25/2010.
|
|
Project Location |
Description |
In Design |
Bid
Let |
Bid Opening |
Award |
Amount |
Contractor |
Notice to Proceed |
Contractual Completion Date |
% Complete |
Notes |
Forks of the Delaware to Locks 22/23 (Easton to Raubsville) |
towpath, prism rehabilitation
|
complete
|
6/11/07
|
7/10/07
|
3/1/08
|
$10,720,410
|
Popple Construction
|
3/3/08
|
2/26/09
|
100%
|
|
Locks 22/23 to Bridgeton Hill Road (Raubsville to Upper Black Eddy) |
towpath, prism rehabilitation
|
complete
|
5/5/08
|
6/17/08
|
7/23/08
|
$8,775,615
|
Nimaris Construction
|
9/12/08
|
9/22/09
|
100% |
|
Bridgeton Hill to Odette's (Upper Black Eddy to New Hope) |
towpath, prism rehabilitation
|
complete
|
2/11/09
|
3/12/09
|
4/7/09
|
$3,323,960
|
Popple
Construction
|
5/4/09
|
5/11/10
|
99%
|
|
Odette's to Ferry Road (New Hope to Lower Makefield Twp. |
towpath, prism rehabilitation
|
complete
|
3/19/08
|
4/17/08
|
5/16/08
|
$3,396,456
|
Tri-State Dredging
|
6/26/08
|
7/10/09
contract extended until 4/2010
|
100%
|
|
Easton |
Chain Dam and Fish Ladder repairs |
complete |
6/13/07 |
7/12/07 |
2/28/08 |
$265,664 |
BiState Construction |
2/28/08 |
12/1/08 |
100% |
|
Williams Twp., Raubsville, Durham |
stop gate, waste gate, footbridge, other repairs |
complete |
3/26/08 |
4/29/08 |
5/15/08 |
$330,602 |
Bill Anskis |
6/26/08
|
4/6/09
|
100% |
|
Point Pleasant, Centre Bridge, Bowman's Hill |
Locks 13 & 14, wastegate, other repairs |
complete |
|
12/4/08
|
1/20/09
|
$157,300 |
Road Con,Inc. |
3/27/09 |
9/30/09 |
100% |
|
Lumberville |
Lock 12 repair |
complete |
|
12/18/08 |
3/20/09
|
$137,370 |
Murray Hill Construction
|
5/21/09 |
2/30/10 |
100% |
|
Williams Twp. |
Rocky Falls stop and waste gate repair |
complete |
|
8/18/09 |
10/5/2009 |
$711,911 |
Bill Anskis |
|
5/31/10 |
100% |
|
Reigelsville |
stop and control gate repair |
complete |
|
9/10/09 |
10/5/2009 |
$363,345 |
- Bi-State Construction |
|
6/30/10 |
99% |
|
Easton |
STP stop gate and pedestrian bridge repair |
complete |
6/5/09 |
7/7/09 |
7/31/2009 |
$98,800 |
Toth Bros.
|
9/23/2009 |
4/30/2010 |
100% |
|
Other Projects |
Lower Makefield Twp. and Yardley Borough |
Black Rock Road culvert replacement |
complete |
3/26/09 |
5/15/08 |
6/20/08 |
$2,937,975 |
James D. Morrissey |
8/20/08
|
3/3/09
contract extended to 5/18/2009 |
100% |
|
|
|
|
|