Progress Report

Now that twelve different flood repair and capital project contracts are in various stages of completion, keeping track of progress is quite a task.  In an effort to make the information about each contract and the project as a whole more understandable, the chart below was developed.

The data shown is as of 6/25/2010. 

Project Location

Description

In Design

Bid
Let

Bid Opening

Award

Amount

Contractor

Notice to Proceed

Contractual Completion Date

% Complete

Notes

Forks of the Delaware to Locks 22/23 (Easton to Raubsville)

towpath, prism rehabilitation

complete

6/11/07

7/10/07

3/1/08

$10,720,410

Popple Construction

3/3/08

2/26/09

100%

Locks 22/23 to Bridgeton Hill Road (Raubsville to Upper Black Eddy)

towpath, prism rehabilitation

complete

5/5/08

6/17/08

7/23/08

$8,775,615

Nimaris Construction

9/12/08

9/22/09

100%

 

Bridgeton Hill  to Odette's (Upper Black Eddy to New Hope)

towpath, prism rehabilitation

complete

2/11/09

3/12/09

4/7/09

$3,323,960

Popple

Construction

5/4/09

5/11/10

99%

Odette's to Ferry Road (New Hope to Lower Makefield Twp.

towpath, prism rehabilitation

complete

3/19/08

4/17/08

5/16/08

$3,396,456

Tri-State Dredging

6/26/08

7/10/09

contract extended until 4/2010

100%

Easton

Chain Dam and Fish Ladder repairs

complete

6/13/07

7/12/07

2/28/08

$265,664

BiState Construction

2/28/08

12/1/08

100%

Williams Twp., Raubsville, Durham

stop gate, waste gate, footbridge, other repairs

complete

3/26/08

4/29/08

5/15/08

$330,602

Bill Anskis

6/26/08

4/6/09

100%

Point Pleasant, Centre Bridge, Bowman's Hill

Locks 13 & 14, wastegate, other repairs

complete

12/4/08

1/20/09

$157,300

Road Con,Inc.

3/27/09

9/30/09

100%

Lumberville

Lock 12 repair

complete

12/18/08

3/20/09

 

$137,370

Murray Hill Construction

5/21/09

2/30/10

100%

Williams Twp.

Rocky Falls stop and waste gate repair

complete

8/18/09

10/5/2009

$711,911

Bill Anskis

5/31/10

100%

Reigelsville

stop and control gate repair

complete

9/10/09

10/5/2009

$363,345

- Bi-State Construction

6/30/10

99%

Easton

STP stop gate and pedestrian bridge repair

complete

6/5/09

7/7/09

7/31/2009

$98,800

Toth Bros.

 

9/23/2009

4/30/2010

100%

Other Projects

Lower Makefield Twp. and Yardley Borough

Black Rock Road culvert replacement

complete

3/26/09

5/15/08

6/20/08

$2,937,975

James D. Morrissey

8/20/08

3/3/09

contract extended to 5/18/2009

100%